June 20 update:
Whilst the final work is still happening inside the building Wilshire have already got their new offices up and running. The volume of space in these tenancies is amazing! Exposed services & raw materials makes this unique character space for the CBD. 4.5m stud, end of trip facilities and the ease of a Queen and Lorne St lobby.
Handover begins to the first of our tenants at the end of the month so expect to see the building opening in late August.

June 2020 - Wilshire reception area looking towards the light well.

June 2020 - Wilshire office from lobby looking into reception and boardroom.

February 2020 - looking up into the light well

February 2020 - bluestone pavers that will create the laneway linking Lorne and Queens Streets

February 2020 - Natural light bounces its way down the light well - Level 3.

February 2020 - View from Level 3 down to the laneway and new escalator.

February 2020 - Wilshire fit out underway

September 2019 - New escalator in opening up a new pedestrian link between Queen and Lorne Streets.

September 2019 - Glass going in on Level 3

September 2019 - Level 4 services going in, painting underway

September 2019 - Lightwell installation progressing onto Level 4.

September 2019 - Lightwell glass going in

March 2019 - commercial floor, light-well opened up

March 2019 - commercial floor, just over 1000m2

March 2019 - Retail Queen St, before mezzanine floor is removed

March 2019 - commercial floor, level 8